What happens when a skyscraper is on schedule but apartment sales are slower than expected? We look at AURUS Residences, ONE and Dom Dau to see how much the bank may lend, how much it has already lent and how much buyers have put into escrow. According to property analyst Pyotr Monich’s 11 November estimate, Sber finances the three projects. Planned construction cost is estimated at RUB 347 billion, total credit limits at RUB 345 billion, and escrow balances at RUB 37.6 billion. We found no public confirmation of those amounts from Sber or the developers. The construction estimate for ONE includes its office component. How to read the figures. A credit limit is the maximum the bank agrees to lend. The developer draws funds as construction progresses. If the limit is RUB 100 billion and the bank has advanced RUB 30 billion, RUB 30 billion has been drawn and RUB 70 billion is still available under the agreement. Monich estimates that the bank has advanced RUB 96.3 billion: 32 billion for AURUS, 32.9 billion for ONE and 31.4 billion for Dom Dau. Buyers have deposited RUB 37.6 billion in escrow, about 11% of the credit limit and 39% of the amount drawn. The developer cannot spend these deposits while they remain in escrow. AURUS Residences has 1,774 apartments and ONE has 1,417. The Russian housing information system lists 866 for Dom Dau. We use industry estimates of sales and the monthly pace as inputs to the scenario. AURUS as an example. Of 1,774 apartments, an estimated 63 have sold. At five more sales a month, another 360 would sell over 72 months. This leaves around 1,350 apartments, or 76%, at the planned handover date. The ONE and Dom Dau figures use the same calculation. Changes to the pace or date change the result. Our November 2026 calculation subtracts estimated sales to date (63, 263 and around 40%, respectively) and sales over 72, 55 and 13 months. The Dom Dau pace is based on 42 deals over ten months. Its handover date comes from an October snapshot of the declaration. A one-year shift would reduce its modeled stock by about 50 apartments at the same pace. Credit limits and balances are Monich’s estimates. Under a shared construction contract, buyers pay into an escrow account and the bank holds the money until the required conditions are met. In the meantime the developer uses the project loan to pay for construction. Slower payments mean a smaller escrow balance. Whether that raises interest costs depends on the loan agreement. The Bank of Russia’s key rate was 14% on 13 November. Project loan rates may differ. For scale, a one percentage point change in the effective rate on an unchanged RUB 10 billion balance is worth about RUB 100 million a year. A forecast of future escrow in roubles requires expected prices and payment schedules as well as contract counts. The 450-metre tower nicknamed Jenga in City-2 is at a different stage. The municipal register lists a permit issued on 13 October to Tsentr Innovatsiy LLC. Reports about difficulties securing financing and a detailed-design contractor remain unconfirmed. The tower is outside our three-project calculation. If sales double, the model still leaves about 990 apartments at AURUS, 495 at ONE and 410 at Dom Dau at handover. Discounts can speed up deals while reducing revenue per apartment. Installment plans spread payments over time. Developers therefore track both the number of deals and when buyers pay. For buyers, the practical indicators are the handover deadline and actual progress on site. The unsold share alone does not tell you whether construction will finish on schedule. Sources: Pyotr Monich’s financing estimates of 11 November, the Property Insider sales overview of 10 November, the Russian housing information system and the Bank of Russia. The industry posts are linked. Calculations by Moscow City Guide’s editorial team.Three projects and one bank
How many apartments could remain at handover?
Project Credit limit, RUB bn Escrow, RUB bn Sales per month Unsold at handover AURUS Residences 139.7 3.8 ≈5 ≈1,350 (76%)
November 2032ONE ≈159.7 16.3 ≈6 ≈825 (58%)
June 2031Dom Dau No separate estimate 17.5 ≈4.2 ≈465 (54%)
December 2027
What escrow changes for construction
The 450-metre proposal on Antonova-Ovseenko Street
What could change the result?