EN
RU ZH AR

The most controversial, yet undoubtedly the most ambitious architectural project of the Moscow International Business Center, Moscow City, has towered above the left bank of the Moskva River for more than 25 years. Over that time, it has become known as the “Russian Manhattan,” although its story began at the dawn of capitalism in modern Russia...

History of Moscow City

The construction project of the century began in the mid-1990s on the site of a former stone quarry and excavation pits near Presnenskaya Embankment. It became the first stage of the large-scale Big City development programme, which was originally scheduled for completion in 2020 but has continued beyond that date.

The entire development area was divided into 20 plots. The original plan called for a green zone in the centre, with an underground car park and transport interchange beneath it. The buildings were to be arranged around the park in a horseshoe shape, with their heights increasing in a spiral.

In practice, the project developed differently. Afimall shopping centre was built on the planned park site, while several other facilities were abandoned.

Developers’ interest in Moscow City continued to grow. This increasingly encouraged architects to focus less on their own ideas about modern real estate and more on future investment. As a result, the planned floor area of the buildings almost doubled, while the utilities installed at the outset proved unable to meet the needs of the emerging city within a city.

In 1995, insufficient funding caused the project to be suspended for just over ten years. In 2003, however, investors renewed their interest in the site, providing the main impetus for the further development of the MIBC, whose momentum continues to this day.

The first completed Moscow City facility was not a skyscraper but Bagration Bridge. It connected the two banks of the Moskva River, and its opening formed part of the celebrations marking the 850th anniversary of the Russian capital.

The first building in the Moscow City complex was Tower 2000, completed in 2001 and connected to the lobby of Bagration Bridge. It is the only building in the complex located on the right bank of the Moskva River and does not qualify as a skyscraper. Other towers were gradually completed after it, including Naberezhnaya Tower A, B and C, Eurasia, Evolution, Imperia, IQ-quarter and others.

Tower 2000 is the only high-rise building constructed precisely in accordance with the original design.

New records were set throughout the construction period, some of which received worldwide recognition and were entered in the Guinness World Records. Each skyscraper took approximately four to five years to build. High-strength, fire-resistant materials were and continue to be used in their construction.

Total investment in Moscow City exceeded USD 12 billion. Today, the nearly completed skyscraper complex is either admired or criticised, but it leaves few people indifferent. It has a distinctive atmosphere of wealth and success, created by breathtaking panoramic views and the thousands of people with above-average incomes who work and live here.

Construction and Management of the Complex

The principal visionary behind the Moscow City MIBC was architect Boris Tkhor. Together with five specialists, he developed the concept for the future business district in 1991 and proposed that the Moscow authorities transform the industrial area near Expocentre into a modern business centre. Some of the world’s best-known architects and leading architectural practices later contributed to the development:

  • NBBJ;
  • Enka;
  • Mikhail Posokhin;
  • Speech;
  • Gennady Sirota;
  • Peter Schweger;
  • Frank Williams;
  • Sergei Tchoban;
  • Skidmore, Owings and Merrill;
  • Tony Kettle and others.

As a result, the futuristic complex has no single architectural style. Its buildings display elements of neo-constructivism, high-tech architecture and several other styles.

The state unitary enterprise Centre-City was appointed as the technical client and the public authority’s representative responsible for state property management. It oversees the effective management, maintenance, servicing and operation of the Central Core of the complex.

Companies involved in the construction of the MIBC included:

  • Capital Group;
  • Tekhinvest CJSC;
  • AFI Development;
  • Ant Yapı Sanayi ve Ticaret Anonim Şirketi;
  • Strabag.

In 1992, the management company City OJSC was established, later changing its legal form to City PJSC. It continues to manage and develop the MIBC and leases the land beneath the complex. The company is owned by Solvers Group.

City Property Management was established to manage office premises commercially in the Imperia, City of Capitals and Federation towers. Its portfolio includes more than 10,000 square metres of office space. Federation Group Management Company LLC and Capex are also involved in management and operations.

Composition of Moscow City

The Moscow City MIBC covers more than 100 hectares and includes not only skyscrapers but also landscaped areas, car parks, road interchanges, metro stations and helicopter landing pads. Today, it comprises more than 23 major facilities with a combined area exceeding 60 hectares. The following facilities have been completed and commissioned.

Bagration Bridge

The pedestrian bridge was completed in 1997. It is 214 metres long, 16 metres wide and 14 metres high, with a total area of 13,655 square metres. The bridge has two levels connected by numerous staircases and escalators. Its glazed lower level contains one of the city’s largest shopping galleries, covering 2,572 square metres. The upper level features an observation deck offering impressive views of the entire business district, Hotel Ukraina and the river. The bridge is also used for various exhibitions. In terms of functionality, Bagration Bridge has no equivalent in Moscow or elsewhere in Russia.

Tower 2000

This business centre was completed in 2001. It is 130 metres high and has 34 floors, all of which are used as offices.

Afimall City

The shopping and entertainment centre opened in 2011. Today, it contains around 500 shops, restaurants, cafés and entertainment venues. It also includes exhibition areas, a park, an ice rink and other facilities. The complex is divided into four zones representing the distinctive features of each season.

  • height: 53 m;
  • floors: 6;
  • total area: 316,832 sq m;
  • developer and contractor: AFI Development;
  • architect: Mosproekt-2, a state unitary enterprise of the City of Moscow;
  • cost: USD 300 million.

Federation Towers: West and East

Federation Tower has held the title of Europe’s tallest skyscraper. It was designed by Sergei Tchoban and Peter Schweger of the SPEECH architectural practice. The complex consists of two skyscrapers, West and East, with the latter completed in 2016.

  • height: 374 m (East) and 242 m (West);
  • floors: 95 and 63;
  • total area: 443,000 sq m;
  • developer: AEON Development;
  • contractor: Federation Tower CJSC;
  • cost: USD 1.2 billion.

The complex includes offices, commercial premises, apartments and entertainment venues. The East Tower is home to one of Europe’s highest observation decks. The building also has its own car park with 74 spaces.

Mercury City

Completed in 2013, this multifunctional supertall skyscraper combines commercial, cultural, office and residential space. Its three underground levels contain a 437-space car park, retail premises and technical facilities. The building was designed by a team that included Mikhail Posokhin, Frank Williams and Gennady Sirota.

  • height: 338.8 m;
  • floors: 75;
  • total area: 173,960 sq m;
  • developer: Mercury Development;
  • cost: USD 650 million–1 billion.

OKO

OKO, a multifunctional complex with one of Europe’s largest underground car parks, providing 3,400 spaces, was designed by Skidmore, Owings & Merrill LLP and commissioned in 2016. It occupies two plots. One contains an office and administrative building together with a residential tower, while the other contains a public 16-level car park.

  • height: 352 m (South Tower) and 245 m (North Tower);
  • floors: 85;
  • total area: 249,610 sq m;
  • developer: Capital Group;
  • contractor: Ant Yapı Sanayi ve Ticaret Anonim Şirketi.

Eurasia

The Eurasia office and leisure complex, combining offices, restaurants, gyms, shops, a hotel, parking facilities and luxury apartments, was completed in 2014.

  • height: 308.9 m;
  • floors: 72 plus 5 underground levels;
  • total area: 207,542 sq m;
  • developer: MosCityGroup;
  • architect: Swanke Hayden Connell Architects;
  • contractor: Tekhinvest CJSC;
  • cost: USD 250 million.

Naberezhnaya Tower

Completed in 2007, the complex is a prestigious international-class office development. It consists of three buildings of different heights with underground levels, connected by a shared retail atrium.

  • height: 268 m;
  • floors: 17, 27 and 59;
  • total area: 265,602 sq m;
  • developer and architect: Enka;
  • contractor: City Center Investment B.V.;
  • cost: USD 200 million.

City of Capitals

This imposing complex consists of two skyscrapers symbolising Saint Petersburg and Moscow. They are connected by a 17-storey podium and a domed building with an atrium. The complex includes a large car park, offices, gyms, restaurants, cinemas, shops, entertainment venues, presentation halls and luxury apartments. The apartments occupy at least half of the upper floors. The complex was built by the Turkish company Ant Yapı Sanayi ve Ticaret Anonim Şirketi to a design by NBBJ and was completed in 2009.

  • height: 302 m (Moscow) and 257 m (Saint Petersburg);
  • floors: 76 (Moscow), 65 (Saint Petersburg) and 17 (domed building);
  • total area: 288,680 sq m;
  • developer: Capital Group;
  • cost: USD 450 million.

Northern Tower

This business centre received BREEAM certification for its landscaping. It contains offices, cafés, a concert hall, a fitness centre, a medical facility and parking. Northern Tower was completed in 2008.

  • height: 108 m;
  • floors: 27;
  • total area: 135,000 sq m;
  • developer: Northern Tower;
  • architect: Design Institute No. 2;
  • contractor: Strabag.

IQ-quarter

This is Moscow City’s main transport interchange, designed to connect the district with Sheremetyevo and Vnukovo airports by rail. The complex was commissioned in 2016. It combines a hotel, parking facilities, an office building, residential premises and retail space.

  • height: 172.8 m;
  • floors: 22 (hotel), 34 and 43;
  • total area: 228,000 sq m;
  • developer: Hals-Development;
  • architect: NBBJ;
  • contractor: Ant Yapı Sanayi ve Ticaret Anonim Şirketi.

Imperia

The complex is known as a vertical city because it efficiently combines commercial, office and residential space. It was completed in 2011.

  • height: 238.6 m;
  • floors: 60;
  • total area: 203,191 sq m;
  • developer: Solvers;
  • architect: NBBJ;
  • contractor: Enka.

Evolution

The strikingly twisted Evolution Tower was completed in 2015. It contains offices, retail premises and restaurants.

  • height: 255 m;
  • floors: 54;
  • total area: 169,000 sq m;
  • developer: Snegiri;
  • architect: Tony Kettle;
  • contractor: City-Palace LLC.

Projects Under Construction

Five projects were still under construction. These included the two Neva Towers, planned at 337 metres for the 79-storey residential building and 290 metres for the 65-storey office building.

Other projects included:

  • a multifunctional complex on Plot No. 15 containing offices and apartments;
  • a multifunctional complex on Plot No. 4 with 71 floors of apartments and offices;
  • a multifunctional complex on Plot No. 20 with 54 floors of offices, apartments and infrastructure facilities;
  • the 10-storey City Point business centre;
  • One Tower.

Transport Accessibility

The Moscow City MIBC was conceived as a way to reduce pressure on the historic centre of the capital. It therefore benefits from good transport connections. The following roads are located nearby:

  • the Third Ring Road;
  • Zvenigorodskoye Highway;
  • Kutuzovsky Avenue;
  • Krasnogvardeysky Passage;
  • Presnenskaya Embankment.

All roads in the Moscow City area have been reconstructed. However, morning traffic congestion remains an issue and requires further solutions. New roads and multilane expressways are therefore planned to connect Moscow City with the capital’s main transport arteries. Both underground and surface car parks are available within the complex for private vehicles.

Moscow City can also be reached by metro. The following stations are located 300–500 metres from different skyscrapers:

  • Vystavochnaya;
  • Delovoy Tsentr;
  • Mezhdunarodnaya.

IQ-quarter contains a transport interchange intended to provide fast rail access to the wider Big City district from Sheremetyevo and Domodedovo airports.

Show more Hide

History of Moscow-City

1991. Beginning of the Moscow City project
1991. Beginning of the Moscow City project

The construction of the century began in the mid-90s on the site of a former quarry and quarries in the area of Presnenskaya Embankment. It became the initial stage of the implementation of the large-scale program "Big City" . The initiator of the idea was the architect Boris Ivanovich Thor.

1991
1992. Continuation of design
1992. Continuation of design

Continuation of the design of the Moscow International Business Center "Moscow-City". The management company OAO "City" (today PAO "City") was organized. It is still engaged in the management and development of the MIBC, and is also the lessee of the land under the complex. Its owner is the "Solvers" group.



1992
1993. Preparatory work and site clearance
1993. Preparatory work and site clearance

Preparatory work is underway and issues are being resolved regarding the clearing of the territory from existing buildings for the construction of the future City. A documentary base is being developed regulating the planned development of Moscow-City.



1993
1996. Beginning of construction of the Bagration Bridge and Tower 2000
1996. Beginning of construction of the Bagration Bridge and Tower 2000

The beginning of construction of the pedestrian bridge Bagration” across the Moscow River and the first tower of the City – “Tower 2000” . Investments amounted to approximately 100 million US dollars. The objects were built according to the initial project of Boris Thor (the initial development plan was not taken into account further)

1996
1997. The Bagration Bridge was built
1997. The Bagration Bridge was built

The Bagration pedestrian bridge (named after the commander-in-chief of the 2nd Western Army at the beginning of the war of 1812, Pyotr Bagration) was opened. Its length is 214 m, width 16 m, and height 14 m. The total area of the bridge is 13,655 sq. m. The bridge has 2 levels connected by numerous stairs and escalators.

1997
2001. The “Tower 2000” was built
2001. The “Tower 2000” was built

“Tower 2000” (the building of the “Reforma” foundation - the original name) was completed in 2001. Its height is 130 m. “Tower 2000” has 34 floors, all of which are reserved for offices.

2001
2002. Launch of the Eurasia Tower project
2002. Launch of the Eurasia Tower project

The Eurasia project was launched. It involved the construction of a 71-story office and hotel complex with a total area of 208.3 thousand square meters in Moscow City.


2002
2003. Launch of the “Towers on the Embankment” project
2003. Launch of the “Towers on the Embankment” project

The project "Towers on the Embankment" developed by architects Inan Vehbi and Osturk Olcay was started by the Turkish company Enka. It was completed in 2003 and Enka immediately began construction of the first object. This was made possible by the fact that the project was divided into 3 parts.

2003
2004. Start of the project “City of Capitals”
2004. Start of the project “City of Capitals”

The Capital City project began construction in 2003, but was soon frozen after changes were made to the complex's design. Construction resumed in 2005.

2004
2004. Launch of construction of the multifunctional complex “Federation”
2004. Launch of construction of the multifunctional complex “Federation”

Construction of the Federation complex begins on the 3rd section of the Moscow International Business Center. The foundation is based on a massive concrete slab made of 14 thousand cubic meters of concrete (recorded in the Guinness Book of Records)

2004
2004. Block A “Tower on the Embankment” was commissioned
2004. Block A “Tower on the Embankment” was commissioned

Delivery and commissioning of the 17-storey building of the complex "Tower on the Embankment" block "A"

2004
2004. Construction of the Northern Tower complex was launched
2004. Construction of the Northern Tower complex was launched

Start of construction of the Northern Tower complex   - one of the lowest buildings in Moscow City.

2004
2004. Start of work on the central core of Moscow-City
2004. Start of work on the central core of Moscow-City

Laying the foundation stone for the Central Core building (TRC "Afimall", "Novotel") one of the most complex in terms of design buildings of the Moscow-City International Business Center, located on plots 6, 7 and 8.

2004
2005. Start of designing the Evolution Tower
2005. Start of designing the Evolution Tower

The Scottish bureau RMJM begins designing the "City Palace Tower" (later the "Evolution" tower) in the form of a spiral as a projection of the "yin-yang" symbol, symbolizing a dancing couple - the bride and groom. A wedding palace was planned at the foot, but this idea was later abandoned.

2005
2005. Block B “Tower on the Embankment” was commissioned
2005. Block B “Tower on the Embankment” was commissioned

The construction company ENKA has commissioned a 27-storey building of the complex "Tower on the Embankment" block "B" (block B)

2005
2005. Design of the Mercury Tower
2005. Design of the Mercury Tower

Design of Mercury City Tower (Mercury Tower, Golden Tower) on Lot 14 begins

2005
2006. Construction of the business complex “Empire” began
2006. Construction of the business complex “Empire” began

Start of construction of the building of the business complex "Empire" (first stage). Initially, on the 4th plot, a multifunctional leisure complex "Aquapark" with a hotel with a total area of 61,322 m² was to be built.

2006
2007. The last block of the “Tower on the Embankment” complex was completed
2007. The last block of the “Tower on the Embankment” complex was completed

The construction of the final building "Tower on the Embankment" (block C) is completed. The 60-story tower is 4 meters higher than the Moscow Triumph Palace and in 2007 became the tallest building in Russia and Europe.

2007
2007. Work on the project of the tower "Russia"
2007. Work on the project of the tower "Russia"

The beginning of construction work on the Rossiya Tower on site 17-18 of the Moscow-City International Business Center.

2007
2007. The Northern Tower complex was completed
2007. The Northern Tower complex was completed

The construction of the Northern Tower has been completed. The building was the third to be commissioned in the City area after Tower 2000 and the Embankment Tower.

2007
2008. Construction of the Evolution Tower began
2008. Construction of the Evolution Tower began

Construction of the Evolution skyscraper begins. In August 2011, Gazprombank opened a 7-year credit line of $345 million for the developer of the Evolution Tower to complete construction.

2008
2008. Launch of construction of the Eurasia Tower
2008. Launch of construction of the Eurasia Tower

Construction has begun on the Eurasia Tower, the only steel tower in Moscow City; all the others are made of concrete.

2008
2009. The multifunctional complex “City of Capitals” was built
2009. The multifunctional complex “City of Capitals” was built

On plot 9, the construction of the multifunctional complex "City of Capitals" has been completed - a complex of two high-rise towers: "Moscow" (73 floors) and "Saint Petersburg" (65 floors) with an 18-story connecting part on plot 9 of the Moscow-City district

2009
2009. Zero cycle of the MFC "Mercury" and slowdown of works
2009. Zero cycle of the MFC "Mercury" and slowdown of works

The zero cycle of works has been completed - the "wall in the ground" and underground floors of the multifunctional complex "Mercury Tower" , although the project was initially planned to be completed in 2009, but the developer "Mercury Development" preferred to slow down the work so as not to bring the facility to the market during the crisis.

2009
2010. Start of construction of the “IQ-quarter”
2010. Start of construction of the “IQ-quarter”

Construction of the IQ-quarter tower has begun, consisting of 3 buildings with a total area of 425,800 m2.

2010
2010. The City of Capitals in the TOP-10 Skyscrapers of the World
2010. The City of Capitals in the TOP-10 Skyscrapers of the World

The Moscow Tower in the Capital City multifunctional complex was included in the TOP-10 best skyscrapers in the world as part of the Emporis Skyscraper Award (Emporis Standards), awarded for its aesthetic appearance and compatibility with the urban environment.

2010
2011. Opening of the AfiMall City complex
2011. Opening of the AfiMall City complex

On May 22, 2011, the grand opening of the shopping and entertainment complex "AfiMall City" (Central Core) took place.

2011
2011. The business center “Empire” was put into operation
2011. The business center “Empire” was put into operation

Commissioning of a 60-storey skyscraper building - the Empire Business Center .

2011
2012. “City of Capitals” took 1st place among skyscrapers in Europe
2012. “City of Capitals” took 1st place among skyscrapers in Europe

The Capital City multifunctional complex took first place among European skyscrapers in the tournament of the most popular buildings at the SkyscraperCity forum, but failed to reach the finals in the world tournament, losing by only 8% to the famous New York skyscraper Empire State Building.

2012
2012. Launch of construction of the OKO multifunctional complex
2012. Launch of construction of the OKO multifunctional complex

Construction of the OKO multifunctional complex , a skyscraper complex located on site 16 Moscow-City, has begun. The name OKO is an abbreviation for "unified crystal bases"

2012
2013. The Mercury Tower was completed
2013. The Mercury Tower was completed

The construction of the 75-storey skyscraper with an orange façade , Mercury City Tower , has been completed. Even before the work is completed (the upper mark of the structure is 340.1 meters), it has become the tallest building in Europe, overtaking London's The Shard skyscraper.

2013
2013. Launch of the “Grand Tower” project
2013. Launch of the “Grand Tower” project

On site 15, construction of the 62-storey building "Grand Tower" (Grand Tower Moscow City) has begun (the project was frozen for a long time, but work resumed in 2019).

2013
2013. Construction of the Neva Towers complex began
2013. Construction of the Neva Towers complex began

Construction has begun on the high-rise complex "Neva Towers" , occupying plots 17 and 18. Earlier, it was planned to build the "Russia" tower with a record height of 612 meters on this site.

2013
2013. Launch of the second stage of the tower “Empire II”
2013. Launch of the second stage of the tower “Empire II”

It became known about the construction of the second stage of the tower "Imperia Tower Imperia" . The project consisted of 2 separate buildings with an area of 115,800 m², on a common stylobate with underground parking and a park, which is located on an overpass and connects the complex with the embankment of the Moscow River.

2013
2014. The Evolution Tower multifunctional complex was completed
2014. The Evolution Tower multifunctional complex was completed

The construction of the multifunctional complex "Evolution Tower" has been completed. Each floor (there are 51 of them) is turned relative to the previous one by 3 degrees, thus the building is "twisted" by 156 degrees.

2014
2014. Construction of the Eurasia Tower is completed
2014. Construction of the Eurasia Tower is completed

Construction of the business center has been completed "Eurasia" is a 309 m high skyscraper located on the 12th section of the City.

2014
2014. “Federation Tower” is the tallest building in Russia and Europe
2014. “Federation Tower” is the tallest building in Russia and Europe

On November 25, 2014, when the top mark of the Vostok Tower of the Federation Complex under construction reached 343 meters, the Federation Tower became the tallest building in Russia and Europe.

2014
2015. Evolution Tower - finalist of “CTBUH Awards 2015”
2015. Evolution Tower - finalist of “CTBUH Awards 2015”

The Evolution Tower became the best glass and translucent structure project at the IV Russian architectural competition “Glass in Architecture”, a finalist of the Best Skyscrapers of the World competition “CTBUH Awards 2015” in the nomination “Best High-Rise Building in Europe” and the winner of the NOPRIZ competition as “Best MFC Project”

2015
2016. The project of the Vostok Tower of the Federation Tower multifunctional complex was completed
2016. The project of the Vostok Tower of the Federation Tower multifunctional complex was completed

The construction of the Vostok skyscraper (previously known as Tower A), a complex of high-rise buildings called the Federation Tower, has been completed. The Vostok Tower has 102 floors (including 95 above-ground and 7 underground), and 18 high-speed elevators are installed in it.

2016
2016. The skyscrapers of the multifunctional complex “OKO” were built
2016. The skyscrapers of the multifunctional complex “OKO” were built

On plot 16, two skyscrapers of the OKO multifunctional complex were built, one of which has 49 floors and is 245 meters high (North Tower), and the other has 85 floors and is 354 meters high (South Tower).

2016
2016. The IQ-quarter project was completed
2016. The IQ-quarter project was completed

On site 11, work has been completed on the IQ-quarter multifunctional complex (IQ Quarter) , consisting of three towers, including offices, apartments, a café, a hotel, parking, and a skating rink.

2016
2017. The Federation Tower project is fully completed
2017. The Federation Tower project is fully completed

On November 15, 2017, the construction of the 374-meter-high Federation Tower complex was fully completed. The International Council on Tall Buildings and Urban Habitat (CTBUH) recognized it as the tallest skyscraper in Europe for 2017. The skyscrapers stand on a slab of 14 cubic meters of concrete, a fact that is included in the Guinness Book of Records.

2017
2018. Start of construction of the Capital Towers complex
2018. Start of construction of the Capital Towers complex

Start of construction of a complex of 3 towers of the Capital Towers complex (two 212 meters high and the dominant 270 meters high) with apartments, not apartments in the City (City Tower, River Tower and Park Tower)

2018
2019. Commissioning of the first stage of Neva Towers
2019. Commissioning of the first stage of Neva Towers

The first stage of Neva Towers has been put into operation, including a 79-story tower with 848 apartments.

2019
2019. “Federation Tower” - “The best real estate in the world” – Grand Prix of the International Property Awards
2019. “Federation Tower” - “The best real estate in the world” – Grand Prix of the International Property Awards

Federation Tower has won the world-famous and honorable quality mark in the field of real estate – the Grand Prix of the International Property Awards 2019-2020 - “The best real estate in the world”

2019
2019. Start of construction of the Headliner residential complex
2019. Start of construction of the Headliner residential complex

In 2019, construction of a new residential complex Headliner, consisting of 10 buildings, began near Moscow-City.

2019
2019. Start of construction of the supertall skyscraper ONE TOWER
2019. Start of construction of the supertall skyscraper ONE TOWER

In 2019, construction began on the multifunctional 109-storey residential complex One Tower (1 Tower) with a height of 442.8 m.

2019
2020. Start of construction of the iCity office skyscraper
2020. Start of construction of the iCity office skyscraper

Construction has begun on the iCity office skyscraper, consisting of two towers, Time Tower (141.2 meters) and Space Tower (256.7 meters)

2020
2020. The Neva Towers business complex is completed
2020. The Neva Towers business complex is completed

Commissioning of the 2nd 68-storey tower of the Neva Tower s complex and completion of the entire complex.

2020
2022. A new 400-meter Palitra tower is planned
2022. A new 400-meter Palitra tower is planned

A new project of a 400-meter tower with the working title Palitra in Moscow-City in the style of K. Malevich from Gals Development has been announced

2022
2022. The Grand Tower skyscraper under construction is renamed Moscow Towers
2022. The Grand Tower skyscraper under construction is renamed Moscow Towers

New skyscraper Grand Tower Moscow City has received the official name Moscow Towers

2022
2023. Construction of the multifunctional complex Dom Dau has been approved
2023. Construction of the multifunctional complex Dom Dau has been approved

Start of construction of the 85-storey residential complex "Dom Dau" near Moscow-City

2023
2024. Construction of Moscow Towers completed
2024. Construction of Moscow Towers completed

NF Group has completed construction of the multifunctional complex Moscow Towers .

2024
2024. The first cube of concrete was poured into the foundation of the Dau House
2024. The first cube of concrete was poured into the foundation of the Dau House

July 30, 2024 at the construction site "Dau House" Pouring of the foundation slab has begun in Moscow City.

2024
2025. Wildberries&Russ headquarters project and Bagration Bridge reconstruction approved
2025. Wildberries&Russ headquarters project and Bagration Bridge reconstruction approved

The Moscow Committee for Architecture has approved the project for the Wildberries&Russ business center, which will appear on Krasnopresnenskaya Embankment next to the Bagration Bridge in Moscow-City.

2025
2025. The One Tower residential complex project has been approved
2025. The One Tower residential complex project has been approved

MR Group announced an updated concept for the One Tower residential complex on the first site of Moscow City. Two towers up to 91 storeys high will be connected by a glass bridge. The project was developed by Sergey Kuznetsov and the GENPRO bureau.

2025
2026. Утверждён проект жилого комплекса Aurus Residences
2026. Утверждён проект жилого комплекса Aurus Residences

Страна Девелопмент представила проект Aurus Residences в районе «Сити-2» рядом с Москва-Сити. Две башни высотой до 395 метров (до 96 этажей) разработаны бюро APEX. Завершение строительства запланировано на 2031 год.

2026
2025. The Big City project is only 80% complete
2025. The Big City project is only 80% complete

The Big City project is 80% complete, which means there are many new and exciting projects and solutions ahead. Follow the news with us.

2025
<h2>Development Plans for “Moscow City”</h2> <p> With the completion of construction on the Moscow City International Business Center, the ambitious <a href="/articles/proekt-bolshoy-siti-osobennosti-i-perspektivy/">“Big City”</a> is just getting underway. In the near future, plans call for expanding the project to cover an additional 100 hectares of land adjacent to the Presnenskaya Embankment, all the way to Khoroshevskoye Highway. </p> <p> Following the reorganization of the future development zone and the removal of industrial facilities in the surrounding areas, plans call for the construction of administrative and business complexes, retail and recreational complexes, as well as residential buildings. The plan is to build approximately 21 million square meters of real estate, which will require more than $100 billion in investment. </p> <p> The “World Trade Center” has already been built as part of the project. Construction of the “Mirax Plaza” hotel and business complex has recently begun, and the “Paradise Life” project has received approval from the authorities. </p> <p> Once all plans are implemented, “Bolshoi City” will become a new and highly prestigious district of the capital. </p>

Any questions about the City?

Ask us. We know everything about Moscow-City.

By sending a message you agree to the privacy policy
personal data processing
and user agreement