Excavation continues for the Wildberries tower in Moscow City

29.11.2026
4 views
0
Wildberries tower construction update with an archival Moscow City skyline

Below-ground work continues on Krasnopresnenskaya Embankment, at the site of the future Wildberries and Russ headquarters. A photo taken from the 89th floor and posted on SkyscraperCity on 29 November shows a braced excavation by Bagration Bridge. Published design figures place the bottom of the foundation slab about 30 metres below ground. Groundwater monitoring documents give a tower height of 439.7 metres.

What is happening on site

In August, crews were installing utilities and working on the building’s foundations at plot 16/1. In September, supplier TMPZ Mekhanika reported delivering 1,180 mm casing pipes for bored piles. Casing supports the sides of the borehole during drilling. Photos from early November show drilling equipment, while later views show the site against the neighbouring towers.

The groundwater monitoring specification gives 30.6 metres as the depth to the underside of the slab. The design includes six underground levels. The photographs show the retaining walls, steel braces and site equipment. The developer has not published the current depth, volume of soil removed or number of completed piles.

Indicative excavation section showing 30.6 metres to the underside of the slab

Design depth to the bottom of the slab, 30.6 metres. Diagram not to scale.

On 24 November, Mosvodokanal opened a tender to design and build sewer connections for the business centre. Bids are due by 10 December.

How tall will the tower be?

The monitoring specification describes an 80-storey tower reaching 439.7 metres, about 42 metres above the initially announced 398 metres. At that height Bagration would be 66 metres taller than the East Tower of the Federation complex (373.7 metres), Moscow’s tallest completed building.

TASS reported a height of 399.8 metres on 20 November, citing the project’s technical and economic figures. The published site development plan sets a 400-metre limit. The city register lists building permit No. 77-01-022204-2025, issued to Parom LLC on 10 July 2025. Public records have yet to confirm a revised permit or zoning rules allowing a tower of nearly 440 metres. RWB has not publicly explained the discrepancy.

Published heights: Bagration 439.7 and 399.8 metres, Federation East 373.7 metres

Two published heights for Bagration, 439.7 and 399.8 metres, compared with Federation East at 373.7 metres.

When will Bagration open?

TASS gives 10 July 2030 as the planned opening date, early in the third quarter. The tower will house Wildberries and Russ. The piling equipment supplier identifies WB Engineering as the technical client. Global Capital Construction names the site in its job listings, while the general contractor named in the contract remains unverified.

Leave your comment or question
Rate the publication
2.5 of 5

Read also

Five towers by the Moskva River. What we know about the Kutuzovsky project
11/28/2026
Five towers by the Moskva River. What we know about the Kutuzovsky project
Five residential towers with 2,185 apartments are planned on the site ...
Editorial illustration for the court ruling in the MoscaEx owner’s case
11/25/2026
Court remands Moscow City’s MoscaEx owner in custody in kidnapping case
Moscow’s Zamoskvoretsky District Court remanded Said Surkhaev in custo...
Moscow City skyline with the Bagration tower’s planned opening in July 2030
11/20/2026
Moscow City’s Bagration tower is scheduled to open in July 2030
TASS reports a planned opening date of July 10, 2030, for the Wildberr...
Moscow City paid zone from December 12, 2026: boundaries and exemptions under Decree No. 2988-PP
11/18/2026
Moscow City paid zone from December 12: boundaries and exemptions under Sobyanin’s decree
Decree No. 2988-PP defines the paid zone and conditional free access f...
Rendering of Sezar Tower in Moscow City with its faceted facade designed by SPEECH
11/17/2026
Construction starts on Sezar Tower in Moscow City, with panoramic lifts to its rooftop restaurant
Workers have completed 257 piles to a depth of 55 metres. Sezar Group’...

Other news in Moscow-City

Five towers by the Moskva River. What we know about the Kutuzovsky project
28.11.2026
Five towers by the Moskva River. What we know about the Kutuzovsky project
Five residential towers with 2,185 apartments are planned on the site ...
Editorial illustration for the court ruling in the MoscaEx owner’s case
25.11.2026
Court remands Moscow City’s MoscaEx owner in custody in kidnapping case
Moscow’s Zamoskvoretsky District Court remanded Said Surkhaev in custo...
Moscow City skyline with the Bagration tower’s planned opening in July 2030
20.11.2026
Moscow City’s Bagration tower is scheduled to open in July 2030
TASS reports a planned opening date of July 10, 2030, for the Wildberr...
Moscow City paid zone from December 12, 2026: boundaries and exemptions under Decree No. 2988-PP
18.11.2026
Moscow City paid zone from December 12: boundaries and exemptions under Sobyanin’s decree
Decree No. 2988-PP defines the paid zone and conditional free access f...
Rendering of Sezar Tower in Moscow City with its faceted facade designed by SPEECH
17.11.2026
Construction starts on Sezar Tower in Moscow City, with panoramic lifts to its rooftop restaurant
Workers have completed 257 piles to a depth of 55 metres. Sezar Group’...
Project rendering of the multilevel water feature in the TOP TOWER podium garden
12.11.2026
A multilevel water feature will anchor the TOP TOWER rooftop garden
A multilevel water feature covering around 100 sq m is planned for TOP...
Archive view of the Moskva River and Belorussky Bridge from Shelepikhinsky Bridge, May 2025
11.11.2026
Riverside promenade opposite Moscow City now reaches the Fomenko Theatre
A 1.2 km stretch opened from the Belorussky Bridge to the Fomenko Thea...
Capital Towers on the right in an archive photo from the 2nd Magistralnaya Street overpass
11.11.2026
Capital Towers near Moscow City displays lights moving up its façades
A November video by Artemy Lebedev shows light streaks rising up Capit...
Shelepikha and the Moscow City towers from Shelepikhinsky Bridge, May 2025. The cover shows 1.04 million square metres of offices under construction.
10.11.2026
More than one million square metres of offices are under construction around Moscow City
Greater City has 1.04 million sq m of offices under construction outsi...
Editorial collage of a raised entrance barrier and road camera against the Moscow City skyline
06.11.2026
Moscow City to replace entrance barriers with cameras from 12 December
Moscow City is set to introduce camera-controlled entry on 12 December...
Architectural rendering of Light City façades in Greater City
05.11.2026
Light City in Greater City: Building A rises as phase two receives approval
Construction continues at Light City. We review October photographs of...
More than 1,000 passengers used the Moscow City stop during the first month of Lastochka service
04.11.2026
More than 1,000 passengers used the Moscow City stop during the first month of Lastochka service
The Federal Passenger Company has reviewed the first month of Lastochk...
Supply of new offices for sale in Moscow City grew eightfold in nine months
03.11.2026
Supply of new offices for sale in Moscow City grew eightfold in nine months
Since January, the supply of new offices in Moscow City has risen from...
Severstal supplied 8,600 tonnes of steel for the columns of One Tower in Moscow City
02.11.2026
Severstal supplied 8,600 tonnes of steel for the columns of One Tower in Moscow City
A total of 8,600 tonnes of S440 rolled steel has been supplied for the...
Visualisations released of a 450-metre “Jenga” tower near Moscow City
01.11.2026
Visualisations released of a 450-metre “Jenga” tower near Moscow City
A 450-metre residential tower is being designed on Antonova-Ovseenko S...
Three pedestrian zones have been established in Moscow City: what has changed in the first phase
29.10.2026
Three pedestrian zones have been established in Moscow City: what has changed in the first phase
The main work on the first phase of the Moscow City improvement projec...
IQ Quarter: Court Refuses to Waive Facade Repair Fees Following UAV Incident
27.10.2026
IQ Quarter: Court Refuses to Waive Facade Repair Fees Following UAV Incident
The court dismissed the lawsuit challenging the fees for repairing the...
The excavation for the "Rossiya" center in Moscow City is more than 90% complete
26.10.2026
The excavation for the "Rossiya" center in Moscow City is more than 90% complete
Near Moscow City, more than 650,000 cubic meters of soil have been exc...
From Leningradskoye Highway to Moscow City: How the New Road Along the MCC Is Being Built
22.10.2026
From Leningradskoye Highway to Moscow City: How the New Road Along the MCC Is Being Built
New photos of the construction of the road to Moscow City near Streshn...