Below-ground work continues on Krasnopresnenskaya Embankment, at the site of the future Wildberries and Russ headquarters. A photo taken from the 89th floor and posted on SkyscraperCity on 29 November shows a braced excavation by Bagration Bridge. Published design figures place the bottom of the foundation slab about 30 metres below ground. Groundwater monitoring documents give a tower height of 439.7 metres.
What is happening on site
In August, crews were installing utilities and working on the building’s foundations at plot 16/1. In September, supplier TMPZ Mekhanika reported delivering 1,180 mm casing pipes for bored piles. Casing supports the sides of the borehole during drilling. Photos from early November show drilling equipment, while later views show the site against the neighbouring towers.
The groundwater monitoring specification gives 30.6 metres as the depth to the underside of the slab. The design includes six underground levels. The photographs show the retaining walls, steel braces and site equipment. The developer has not published the current depth, volume of soil removed or number of completed piles.

Design depth to the bottom of the slab, 30.6 metres. Diagram not to scale.
On 24 November, Mosvodokanal opened a tender to design and build sewer connections for the business centre. Bids are due by 10 December.
How tall will the tower be?
The monitoring specification describes an 80-storey tower reaching 439.7 metres, about 42 metres above the initially announced 398 metres. At that height Bagration would be 66 metres taller than the East Tower of the Federation complex (373.7 metres), Moscow’s tallest completed building.
TASS reported a height of 399.8 metres on 20 November, citing the project’s technical and economic figures. The published site development plan sets a 400-metre limit. The city register lists building permit No. 77-01-022204-2025, issued to Parom LLC on 10 July 2025. Public records have yet to confirm a revised permit or zoning rules allowing a tower of nearly 440 metres. RWB has not publicly explained the discrepancy.

Two published heights for Bagration, 439.7 and 399.8 metres, compared with Federation East at 373.7 metres.
When will Bagration open?
TASS gives 10 July 2030 as the planned opening date, early in the third quarter. The tower will house Wildberries and Russ. The piling equipment supplier identifies WB Engineering as the technical client. Global Capital Construction names the site in its job listings, while the general contractor named in the contract remains unverified.