The excavation for the "Rossiya" center in Moscow City is more than 90% complete

26.10.2026
591 views
0
The excavation for the "Rossiya" center in Moscow City is more than 90% complete

At the construction site of the “Russia” National Center near Moscow City, work on the excavation is nearing completion: it is more than 90% complete. More than 650,000 cubic meters of soil have already been excavated. These figures were published by the Moscow Construction Complex on October 26, 2026.

Meanwhile, construction of the future building’s foundation is already underway. Earthwork and the pouring of the foundation slab are proceeding simultaneously in various sections of the site—this approach helps reduce construction time.

Why do the reports mention 90% and 97%?

These figures refer to different stages of work. Over 90% refers to the overall readiness of the excavation. And according to Moscow Deputy Mayor Vladimir Efimov, the 97% figure represents the proportion of soil already excavated out of the total planned volume. Neither of these figures indicates the same level of completion for the entire National Center.

Инфографика: котлован центра «Россия» готов более чем на 90%, выбрано около 97% грунта — свыше 650 тыс. кубометров.

There is an active metro line beneath the construction site

Construction is underway on the site of the former “Expocenter” on Krasnopresnenskaya Embankment. Here, both groundwater and the proximity of active metro tunnels must be taken into account. We covered how the excavation pit is being constructed above the metro lines in a separate article.

According to city authorities, the site is using “wall-in-ground” technology for the retaining wall, along with anchor fastenings and a dewatering system. Work continues on installing the bracing system, reinforcing the slab, and waterproofing. Soil conditions are being monitored by specialists.

More than 600 people and 127 pieces of equipment are working at the construction site. A total of about 150,000 cubic meters of concrete will be needed for the foundation slab.

What’s Next

The new report does not specify a completion date for the entire Phase Zero. The center is still scheduled to open in 2029. Construction of the main complex constitutes the first phase of the project; the second phase includes an underground bus parking garage and a landscaped park.

The main architectural feature of the future building will be its “canopy” roof. For more details about it, the public spaces, and the opening plans, see our news article on the architecture of the “Russia” National Center.

Leave your comment or question
Rate the publication
2.5 of 5

Other news in Moscow-City

Project rendering of the multilevel water feature in the TOP TOWER podium garden
12.11.2026
A multilevel water feature will anchor the TOP TOWER rooftop garden
A multilevel water feature covering around 100 sq m is planned for TOP...
Archive view of the Moskva River and Belorussky Bridge from Shelepikhinsky Bridge, May 2025
11.11.2026
Riverside promenade opposite Moscow City now reaches the Fomenko Theatre
A 1.2 km stretch opened from the Belorussky Bridge to the Fomenko Thea...
Capital Towers on the right in an archive photo from the 2nd Magistralnaya Street overpass
11.11.2026
Capital Towers near Moscow City displays lights moving up its façades
A November video by Artemy Lebedev shows light streaks rising up Capit...
Shelepikha and the Moscow City towers from Shelepikhinsky Bridge, May 2025. The cover shows 1.04 million square metres of offices under construction.
10.11.2026
More than one million square metres of offices are under construction around Moscow City
Greater City has 1.04 million sq m of offices under construction outsi...
Editorial collage of a raised entrance barrier and road camera against the Moscow City skyline
06.11.2026
Moscow City to replace entrance barriers with cameras from 12 December
Moscow City is set to introduce camera-controlled entry on 12 December...
Architectural rendering of Light City façades in Greater City
05.11.2026
Light City in Greater City: Building A rises as phase two receives approval
Construction continues at Light City. We review October photographs of...
More than 1,000 passengers used the Moscow City stop during the first month of Lastochka service
04.11.2026
More than 1,000 passengers used the Moscow City stop during the first month of Lastochka service
The Federal Passenger Company has reviewed the first month of Lastochk...
Supply of new offices for sale in Moscow City grew eightfold in nine months
03.11.2026
Supply of new offices for sale in Moscow City grew eightfold in nine months
Since January, the supply of new offices in Moscow City has risen from...
Severstal supplied 8,600 tonnes of steel for the columns of One Tower in Moscow City
02.11.2026
Severstal supplied 8,600 tonnes of steel for the columns of One Tower in Moscow City
A total of 8,600 tonnes of S440 rolled steel has been supplied for the...
Visualisations released of a 450-metre “Jenga” tower near Moscow City
01.11.2026
Visualisations released of a 450-metre “Jenga” tower near Moscow City
A 450-metre residential tower is being designed on Antonova-Ovseenko S...
Three pedestrian zones have been established in Moscow City: what has changed in the first phase
29.10.2026
Three pedestrian zones have been established in Moscow City: what has changed in the first phase
The main work on the first phase of the Moscow City improvement projec...
IQ Quarter: Court Refuses to Waive Facade Repair Fees Following UAV Incident
27.10.2026
IQ Quarter: Court Refuses to Waive Facade Repair Fees Following UAV Incident
The court dismissed the lawsuit challenging the fees for repairing the...
From Leningradskoye Highway to Moscow City: How the New Road Along the MCC Is Being Built
22.10.2026
From Leningradskoye Highway to Moscow City: How the New Road Along the MCC Is Being Built
New photos of the construction of the road to Moscow City near Streshn...
173 piles for two towers: Fensma Reveals the Foundation Specifications for “Aurus Residences”
20.10.2026
173 piles for two towers: Fensma Reveals the Foundation Specifications for “Aurus Residences”
Fensma has revealed the details of the foundation for “Aurus Residence...
Construction of a 450-meter-tall residential skyscraper has been approved near Moscow City
15.10.2026
Construction of a 450-meter-tall residential skyscraper has been approved near Moscow City
Permission has been granted to build a residential complex with 1,018 ...
One in four establishments in Moscow City is a coffee shop: how the foodservice industry is changing
12.10.2026
One in four establishments in Moscow City is a coffee shop: how the foodservice industry is changing
According to CORE.XP, the share of coffee shops in Moscow City’s food ...
Office space in Moscow City has dropped in price to 40,000 rubles per unit
09.10.2026
Office space in Moscow City has dropped in price to 40,000 rubles per unit
The cost of a workstation at the Moscow City service office has fallen...
The "Russia" National Center near Moscow City: "Pokrov," an amphitheater, and plans for 2029
06.10.2026
The "Russia" National Center near Moscow City: "Pokrov," an amphitheater, and plans for 2029
Natalia Virtuozova confirmed the plan to open on November 4, 2029. Her...
"Sofia" has completed the tunneling work between "SberCity" and "Novorizhskaya"
03.10.2026
"Sofia" has completed the tunneling work between "SberCity" and "Novorizhskaya"
The mayor of Moscow announced the completion of the 2.52 km right tunn...