173 piles for two towers: Fensma Reveals the Foundation Specifications for “Aurus Residences”

20.10.2026
927 views
0
173 piles for two towers: Fensma Reveals the Foundation Specifications for “Aurus Residences”

A total of 173 bored piles with a diameter of 1.65 meters are planned for the two towers of “Aurus Residence” near Moscow City. The maximum drilling depth will be 57.9 meters, and the effective length of each pile will be 34.5 meters. Fensma representatives provided these specifications in an interview with the “Skyscrapers of Russia” channel, published on October 19.

The company is currently carrying out pre-construction work. According to its representatives, this phase is scheduled to last about 16 months. It encompasses the construction of the foundation and the underground portion of the complex—this timeframe should not be considered the time remaining until the completion of the towers.

Nearly 58 meters of drilling—not the length of the pile

The interview separately specifies the drilling depth and the effective length of the piles. Therefore, the statement “173 piles nearly 58 meters long” would be inaccurate: the piles are specified as 34.5 meters long, and the maximum drilling depth is 57.9 meters. The publication does not specify in detail the reference points from which these measurements are taken.

The piles are not driven into the ground here. First, a borehole is drilled; then, a reinforcing cage is installed, and the hole is filled with concrete mix. Fensma representatives emphasize that they monitor verticality, concrete quality, and compliance with design parameters.

Глубина бурения 57,9 метра, рабочая длина сваи 34,5 метра и проектная глубина котлована 25 метров в «Аурус Резиденциях».

Four drilling rigs and a 25-meter-deep excavation

Four drilling rigs, as well as cranes, excavators, and loaders, are being used to install the piles. The stated pace is about ten piles per week. Approximately 130 people are working on the site; once the project reaches peak activity during the zero cycle, the workforce is planned to increase to 150.

The project specifies an excavation depth of 25 meters. This refers to the planned depth of the excavation, not an indication that the soil has already been excavated to that depth. In an editorial addendum to the interview, the channel clarifies: the main soil excavation work is scheduled to begin no later than the 20s of November.

What Is Known About the Timeline

Fensma representatives report that work is proceeding on schedule, and the groundwork phase is estimated to take approximately 16 months. However, the interview does not specify the starting date for this period.

The target date for completion of the pile driving work—June 2027—is mentioned in the interviewer’s question. The same source also refers to the completion of the “retaining wall.” In the response, the company representative discusses preparations for winter conditions but does not specifically confirm this timeline.

The main new detail for those monitoring the construction is the specifications of the foundation for both towers and the stated pace of its construction. Based on this information, it is possible to track the progress of the underground portion of the project without confusing the completion of the excavation wall with the completion of the entire foundation.

Leave your comment or question
Rate the publication
2.5 of 5

Read also

IQ Quarter: Court Refuses to Waive Facade Repair Fees Following UAV Incident
10/27/2026
IQ Quarter: Court Refuses to Waive Facade Repair Fees Following UAV Incident
The court dismissed the lawsuit challenging the fees for repairing the...
The excavation for the "Rossiya" center in Moscow City is more than 90% complete
10/26/2026
The excavation for the "Rossiya" center in Moscow City is more than 90% complete
Near Moscow City, more than 650,000 cubic meters of soil have been exc...
From Leningradskoye Highway to Moscow City: How the New Road Along the MCC Is Being Built
10/22/2026
From Leningradskoye Highway to Moscow City: How the New Road Along the MCC Is Being Built
New photos of the construction of the road to Moscow City near Streshn...
Construction of a 450-meter-tall residential skyscraper has been approved near Moscow City
10/15/2026
Construction of a 450-meter-tall residential skyscraper has been approved near Moscow City
Permission has been granted to build a residential complex with 1,018 ...
One in four establishments in Moscow City is a coffee shop: how the foodservice industry is changing
10/12/2026
One in four establishments in Moscow City is a coffee shop: how the foodservice industry is changing
According to CORE.XP, the share of coffee shops in Moscow City’s food ...

Other news in Moscow-City

Wildberries tower construction update with an archival Moscow City skyline
29.11.2026
Excavation continues for the Wildberries tower in Moscow City
Below-ground works continue by Bagration Bridge. The foundation slab i...
Five towers by the Moskva River. What we know about the Kutuzovsky project
28.11.2026
Five towers by the Moskva River. What we know about the Kutuzovsky project
Five residential towers with 2,185 apartments are planned on the site ...
Editorial illustration for the court ruling in the MoscaEx owner’s case
25.11.2026
Court remands Moscow City’s MoscaEx owner in custody in kidnapping case
Moscow’s Zamoskvoretsky District Court remanded Said Surkhaev in custo...
Moscow City skyline with the Bagration tower’s planned opening in July 2030
20.11.2026
Moscow City’s Bagration tower is scheduled to open in July 2030
TASS reports a planned opening date of July 10, 2030, for the Wildberr...
Moscow City paid zone from December 12, 2026: boundaries and exemptions under Decree No. 2988-PP
18.11.2026
Moscow City paid zone from December 12: boundaries and exemptions under Sobyanin’s decree
Decree No. 2988-PP defines the paid zone and conditional free access f...
Rendering of Sezar Tower in Moscow City with its faceted facade designed by SPEECH
17.11.2026
Construction starts on Sezar Tower in Moscow City, with panoramic lifts to its rooftop restaurant
Workers have completed 257 piles to a depth of 55 metres. Sezar Group’...
Project rendering of the multilevel water feature in the TOP TOWER podium garden
12.11.2026
A multilevel water feature will anchor the TOP TOWER rooftop garden
A multilevel water feature covering around 100 sq m is planned for TOP...
Archive view of the Moskva River and Belorussky Bridge from Shelepikhinsky Bridge, May 2025
11.11.2026
Riverside promenade opposite Moscow City now reaches the Fomenko Theatre
A 1.2 km stretch opened from the Belorussky Bridge to the Fomenko Thea...
Capital Towers on the right in an archive photo from the 2nd Magistralnaya Street overpass
11.11.2026
Capital Towers near Moscow City displays lights moving up its façades
A November video by Artemy Lebedev shows light streaks rising up Capit...
Shelepikha and the Moscow City towers from Shelepikhinsky Bridge, May 2025. The cover shows 1.04 million square metres of offices under construction.
10.11.2026
More than one million square metres of offices are under construction around Moscow City
Greater City has 1.04 million sq m of offices under construction outsi...
Editorial collage of a raised entrance barrier and road camera against the Moscow City skyline
06.11.2026
Moscow City to replace entrance barriers with cameras from 12 December
Moscow City is set to introduce camera-controlled entry on 12 December...
Architectural rendering of Light City façades in Greater City
05.11.2026
Light City in Greater City: Building A rises as phase two receives approval
Construction continues at Light City. We review October photographs of...
More than 1,000 passengers used the Moscow City stop during the first month of Lastochka service
04.11.2026
More than 1,000 passengers used the Moscow City stop during the first month of Lastochka service
The Federal Passenger Company has reviewed the first month of Lastochk...
Supply of new offices for sale in Moscow City grew eightfold in nine months
03.11.2026
Supply of new offices for sale in Moscow City grew eightfold in nine months
Since January, the supply of new offices in Moscow City has risen from...
Severstal supplied 8,600 tonnes of steel for the columns of One Tower in Moscow City
02.11.2026
Severstal supplied 8,600 tonnes of steel for the columns of One Tower in Moscow City
A total of 8,600 tonnes of S440 rolled steel has been supplied for the...
Visualisations released of a 450-metre “Jenga” tower near Moscow City
01.11.2026
Visualisations released of a 450-metre “Jenga” tower near Moscow City
A 450-metre residential tower is being designed on Antonova-Ovseenko S...
Three pedestrian zones have been established in Moscow City: what has changed in the first phase
29.10.2026
Three pedestrian zones have been established in Moscow City: what has changed in the first phase
The main work on the first phase of the Moscow City improvement projec...
IQ Quarter: Court Refuses to Waive Facade Repair Fees Following UAV Incident
27.10.2026
IQ Quarter: Court Refuses to Waive Facade Repair Fees Following UAV Incident
The court dismissed the lawsuit challenging the fees for repairing the...
The excavation for the "Rossiya" center in Moscow City is more than 90% complete
26.10.2026
The excavation for the "Rossiya" center in Moscow City is more than 90% complete
Near Moscow City, more than 650,000 cubic meters of soil have been exc...