iCITY skyscrapers are being built at the 6th floor level.

Construction work on the iCITY skyscraper complex, part of the Moscow-City cluster, is ongoing daily. Experienced MR Group specialists are handling the monolithic construction. Renaissance Construction, a recognized European construction company, has assumed the general contractor's duties.

In buildings T2 and T1, work is being carried out on the sixth and fourth floors, respectively. Last month, at least 7,000 cubic meters of concrete arrived on site for the construction of the new buildings.

To date, the following have been fully completed:

  • excavation pit arrangement;

  • construction of a spacer system.

The Roads and Bridges company is currently constructing temporary access roads. Once they are fully completed, work will begin on the connection to the overpass. A passage to the fifth floor is planned for the next level.

The monolithic sections of the structure, occupying a vast area of the stylobate, reach up to the second floor. Landscape designers chose the building's roof to create a dramatic terrace. A unique translucent dome will be erected above it, connecting the public spaces of both buildings. Comfortable seating areas will be located directly on the terrace, providing excellent conditions for relaxation.

The creation of modern infrastructure for residents and guests is planned:

  • shops;

  • fub-hall;

  • banks;

  • fitness center with a swimming pool;

  • beauty salons;

  • pharmacies;

  • service departments;

  • lounge area.

The total volume of commercial space located here will exceed 9,800 m².

M. Litinetskaya, the developer-managing partner of MR Group, clarifies: "The goals we've set can confidently be called ambitious. We're actively seeking ways to achieve the expected results on time. Work is proceeding at an intensive pace. Several hundred construction professionals are on site every day. The necessary materials are arriving without delay, allowing us to adhere to the planned schedule."

The iCITY complex has been allocated a 2-hectare site. Two towers of different heights are planned:

  • Time Tower, consisting of 61 floors, reaching a height of 257 m;

  • Space Tower, comprising 34 floors and a height of 141 m.

Several stations are located near the towers and are easily accessible on foot. The office center will have separate entrances and exits, allowing access to the Third Ring Road overpass from the underground parking garage. The underground parking garage has over 900 spaces and consists of five levels. Several underground routes will connect iCITY and Moscow City.

Leave your comment or question
Rate the publication
2.5 of 5

Read also

The OKO Tower in Moscow City is a popular wedding venue.
05/22/2022
The OKO Tower in Moscow City is a popular wedding venue.
The Oko Tower, located in the Moscow-City center, has been named as on...
Moscow-City will connect with the business center in Rublevo-Arkhangelskoye
05/21/2022
Moscow-City will connect with the business center in Rublevo-Arkhangelskoye
In the northwestern section of the capital, two modern underground lin...
The world's tallest library will be located in Moscow City.
05/18/2022
The world's tallest library will be located in Moscow City.
An unusual library will open at the Moscow-City International Business...
Reduction in the share of vacant retail space in Moscow City
04/30/2022
Reduction in the share of vacant retail space in Moscow City
40% of retail space available for lease in the capital's business cent...
A decline in demand for apartments in Moscow City is being recorded.
04/27/2022
A decline in demand for apartments in Moscow City is being recorded.
Over the past year, apartments in Moscow City have become less popular...
Five observation decks will appear on the roofs of Moscow skyscrapers.
04/22/2022
Five observation decks will appear on the roofs of Moscow skyscrapers.
Five Moscow skyscrapers are in the near future. will prove to be even ...

Other news in Moscow-City

Moscow City paid zone from December 12, 2026: boundaries and exemptions under Decree No. 2988-PP
18.11.2026
Moscow City paid zone from December 12: boundaries and exemptions under Sobyanin’s decree
Decree No. 2988-PP defines the paid zone and conditional free access f...
Rendering of Sezar Tower in Moscow City with its faceted facade designed by SPEECH
17.11.2026
Construction starts on Sezar Tower in Moscow City, with panoramic lifts to its rooftop restaurant
Workers have completed 257 piles to a depth of 55 metres. Sezar Group’...
Project rendering of the multilevel water feature in the TOP TOWER podium garden
12.11.2026
A multilevel water feature will anchor the TOP TOWER rooftop garden
A multilevel water feature covering around 100 sq m is planned for TOP...
Archive view of the Moskva River and Belorussky Bridge from Shelepikhinsky Bridge, May 2025
11.11.2026
Riverside promenade opposite Moscow City now reaches the Fomenko Theatre
A 1.2 km stretch opened from the Belorussky Bridge to the Fomenko Thea...
Capital Towers on the right in an archive photo from the 2nd Magistralnaya Street overpass
11.11.2026
Capital Towers near Moscow City displays lights moving up its façades
A November video by Artemy Lebedev shows light streaks rising up Capit...
Shelepikha and the Moscow City towers from Shelepikhinsky Bridge, May 2025. The cover shows 1.04 million square metres of offices under construction.
10.11.2026
More than one million square metres of offices are under construction around Moscow City
Greater City has 1.04 million sq m of offices under construction outsi...
Editorial collage of a raised entrance barrier and road camera against the Moscow City skyline
06.11.2026
Moscow City to replace entrance barriers with cameras from 12 December
Moscow City is set to introduce camera-controlled entry on 12 December...
Architectural rendering of Light City façades in Greater City
05.11.2026
Light City in Greater City: Building A rises as phase two receives approval
Construction continues at Light City. We review October photographs of...
More than 1,000 passengers used the Moscow City stop during the first month of Lastochka service
04.11.2026
More than 1,000 passengers used the Moscow City stop during the first month of Lastochka service
The Federal Passenger Company has reviewed the first month of Lastochk...
Supply of new offices for sale in Moscow City grew eightfold in nine months
03.11.2026
Supply of new offices for sale in Moscow City grew eightfold in nine months
Since January, the supply of new offices in Moscow City has risen from...
Severstal supplied 8,600 tonnes of steel for the columns of One Tower in Moscow City
02.11.2026
Severstal supplied 8,600 tonnes of steel for the columns of One Tower in Moscow City
A total of 8,600 tonnes of S440 rolled steel has been supplied for the...
Visualisations released of a 450-metre “Jenga” tower near Moscow City
01.11.2026
Visualisations released of a 450-metre “Jenga” tower near Moscow City
A 450-metre residential tower is being designed on Antonova-Ovseenko S...
Three pedestrian zones have been established in Moscow City: what has changed in the first phase
29.10.2026
Three pedestrian zones have been established in Moscow City: what has changed in the first phase
The main work on the first phase of the Moscow City improvement projec...
IQ Quarter: Court Refuses to Waive Facade Repair Fees Following UAV Incident
27.10.2026
IQ Quarter: Court Refuses to Waive Facade Repair Fees Following UAV Incident
The court dismissed the lawsuit challenging the fees for repairing the...
The excavation for the "Rossiya" center in Moscow City is more than 90% complete
26.10.2026
The excavation for the "Rossiya" center in Moscow City is more than 90% complete
Near Moscow City, more than 650,000 cubic meters of soil have been exc...
From Leningradskoye Highway to Moscow City: How the New Road Along the MCC Is Being Built
22.10.2026
From Leningradskoye Highway to Moscow City: How the New Road Along the MCC Is Being Built
New photos of the construction of the road to Moscow City near Streshn...
173 piles for two towers: Fensma Reveals the Foundation Specifications for “Aurus Residences”
20.10.2026
173 piles for two towers: Fensma Reveals the Foundation Specifications for “Aurus Residences”
Fensma has revealed the details of the foundation for “Aurus Residence...
Construction of a 450-meter-tall residential skyscraper has been approved near Moscow City
15.10.2026
Construction of a 450-meter-tall residential skyscraper has been approved near Moscow City
Permission has been granted to build a residential complex with 1,018 ...
One in four establishments in Moscow City is a coffee shop: how the foodservice industry is changing
12.10.2026
One in four establishments in Moscow City is a coffee shop: how the foodservice industry is changing
According to CORE.XP, the share of coffee shops in Moscow City’s food ...