The most scandalous, but certainly the most grandiose architectural project, the Moscow International Business Center "Moscow City" has been rising on the left bank of the Moscow River for over 25 years. During this time, it has been nicknamed "Russian Manhattan", and it all began at the dawn of domestic capitalism...

History of Moscow-City

The construction of the century began in the mid-90s on the site of a former quarry and quarries in the area of Presnenskaya Embankment. It became the initial stage of the implementation of the large-scale "Big City" program, the completion of which was planned for 2020, but in fact is dragging on.

The entire development area was divided into 20 plots. It was planned to create a green zone in the center, under which there would be an underground parking lot and a transport interchange. The buildings were supposed to be erected around the park in the form of a horseshoe. At the same time, their height was supposed to increase spirally.

In practice, everything turned out differently. The Afimall shopping center was built on the site of the park, and some objects had to be abandoned.

The interest of customers in "Moscow-City" was steadily growing. This forced the architects to be guided not so much by their own ideas about modern real estate , but by future investments. Therefore, the area of the objects being designed gradually increased almost 2 times, and the initially supplied communications were unable to cover the needs of the city under construction in the city.

In 1995, due to a lack of funding, the project was frozen for a little over 10 years. But in 2003, the waning interest of investors in the project flared up again, which served as the main impetus for the development of the MIBC, the inertia of which is still sufficient to this day.

The first object of "Moscow-City" was not a skyscraper tower, but the " Bagration" bridge. It connected the banks of the Moskva River and its opening marked the celebration of the 850th anniversary of the capital of Russia.

The first building of the Moscow-City complex was the "Tower 2000" , completed in 2001, connected to the Bagration lobby. It is the only one of the entire complex that rises on the right bank of the Moscow River and does not claim to be a skyscraper. Following it, other towers gradually began to be completed: Tower on the Embankment A , B , C , Eurasia , Evolution , Empire , I Q-quarter and others.

"Tower 2000" is the only high-rise building that was built exactly according to the original design.

During the construction, new records were set, some of which even earned worldwide recognition and were noted in the Guinness Book of Records. Each skyscraper was built for about 4-5 years. Super-strong and fireproof materials were and are used for their construction.

The total investment in Moscow City has exceeded 12 billion US dollars. Today, the almost finished skyscraper complex is either idolized or hated, but it leaves no one indifferent. There is a special atmosphere of money and success here, created by the breathtaking panorama from the windows and thousands of people with above-average incomes.

Construction and maintenance of the complex

The main ideologist of the Moscow-City MICD was the architect Boris Thor. Together with 5 specialists, he created the concept of the future business center in 1991 and proposed to the capital's authorities to transform the industrial zone near the Expocentre into a modern business center. Later, some of the most famous architects and leading architectural firms contributed to the construction of the complex:

  • NBBJ;

  • Enka;

  • Mikhail Posokhin;

  • Speech;

  • Gennady Sirota;

  • Peter Schweger;

  • Frank Williams;

  • Sergey Tchoban;

  • Skidmore, Owings and Merrill;

  • Tony Kettle and others.

As a result, the futuristic complex does not have a single style. The objects have features of neo-constructivism, high-tech and some other architectural styles.

The technical customer and representative of the authorities for the disposal of state property is the State Unitary Enterprise "Center-City". It is responsible for the effective management, maintenance, service and operation of the Central Core of the complex.

The following companies were involved in the construction of the Moscow International Business Center:

  • Capital Group;

  • JSC Techinvest;

  • AFI Development;

  • Ant Yapı Sanayi ve Ticaret Anonim Şirketi;

  • Strabag.

In 1992, the management company OAO City was organized, which later changed its form of ownership to PAO City. It is still engaged in the management and development of the MIBC, and is also the lessee of the land under the complex. Its owner is the Solvers group.

For the purpose of commercial management of office premises in the towers "Empire", "City of Capitals" and "Federation", the management company "City Property Management" was created. More than 10,000 sq. m of office space were provided for its management. Management and operation are also carried out by OOO "UK Federation Group", "Capex".

Moscow-City team

The Moscow-City International Business Center is spread over more than 100 hectares, where not only skyscrapers are located, but also park areas, car parks, road junctions, metro stations, and helicopter landing pads. Today, it is formed by more than 23 large-scale objects, the total area of which exceeds 60 hectares. Among them, the following objects are completely ready and put into operation.

Bagration Bridge

The pedestrian bridge was commissioned in 1997. It is 214 m long, 16 m wide and 14 m high. The total area of the bridge is 13,655 sq. m. The bridge has 2 levels connected by numerous staircases and escalators. Its lower tier is glazed and is one of the largest shopping galleries in the city, with an area of 2,572 sq. m. The upper level has an observation deck with an impressive view of the entire business district, the Ukraine Hotel and, of course, the river. Today, the bridge premises are also used for various exhibitions. In terms of functionality, Bagration has no equal not only in the capital, but throughout Russia.

"Tower 2000"

This business center was completed in 2001. Its height is 130 m. "Tower 2000" has 34 floors, all of which are reserved for offices.

"Afimall City"

The shopping and entertainment center was put into operation in 2011. Today, it houses about 500 different stores, restaurants, cafes, and entertainment areas. There are also exhibition areas, a park, a skating rink, etc. It is divided into 4 zones, recreating the features of each season.

  • height – 53 m;

  • floors – 6;

  • area of the facility – 316,832 sq. m;

  • developer and builder – AFI Development;

  • architect – State Unitary Enterprise of Moscow “Mosproekt-2”;

  • cost - 300 million dollars.

Federation Towers: West and East

The Federation Tower holds the title of the tallest skyscraper in Europe. Its architects are S. Tchoban and P. Shveger from the Spreech architectural studio. It is formed by two skyscrapers: West and East, the latter of which was completed in 2016.

  • height – 374 m (East) and 242 m (West);

  • floors – 95 and 63;

  • area of the facility – 443,000 sq. m;

  • developer – AEON-Development;

  • developer – Federation Tower CJSC;

  • cost - 1.2 billion dollars.

There are areas for offices, commercial premises, apartments and entertainment venues, including the highest observation deck in Europe in the East Tower. The building also has its own parking lot for 74 cars.

"Mercury City"

Completed in 2013, the multifunctional supertall skyscraper organically combines commercial, cultural, office and residential premises. The three underground floors house a 437-space car park, retail and technical premises. The building's architecture was developed by a group of specialists, including M. Posokhin, F. Williams, and G. Sirota.

  • height – 338.8 m;

  • floors – 75;

  • area of the facility – 173,960 sq. m;

  • developer – Mercury Development;

  • cost – 650 million – 1 billion dollars.

"Eye"

The multifunctional complex with the largest underground parking in Europe (for 3,400 spaces) "Oko" was designed by the bureau "Skidmore, Owings & Merrill LLP" and was put into operation in 2016. It occupies two sites. On one of them there is an office and administrative building and a residential tower. On the second there is a public 16-level parking lot.

  • height – 352 m (south tower) and 245 m (north tower);

  • floors – 85;

  • area of the facility – 249,610 sq. m;

  • developer – Capital Group;

  • developer – Ant Yapı Sanayi ve Ticaret Anonim Şirketi.

"Eurasia"

The office and recreational complex "Eurasia", which combines offices, restaurants, gyms, shops, a hotel, parking and luxury apartments, was completed in 2014.

  • height – 308.9 m;

  • floors – 72+5 underground;

  • area of the facility – 207,542 sq. m;

  • developer – MosCityGroup;

  • Architect – Swanke Hayden Connell Architects;

  • developer – Techinvest CJSC;

  • cost - 250 million dollars.

"Tower on the Embankment"

The complex, completed in 2007, is a representative office building of international class. It consists of three buildings of different heights with underground floors, united into one shopping hall.

  • height – 268 m;

  • floors – 17, 27 and 59;

  • area of the facility – 265,602 sq. m;

  • developer and architect – Enka;

  • developer – City Center Investment B.V.;

  • cost - 200 million dollars.

"City of Capitals"

The majestic complex has 2 skyscrapers symbolizing St. Petersburg and Moscow. They are united by a 17-story base and a domed building with an atrium. It houses a large parking lot, offices, gyms, restaurants, cinemas, shops, entertainment venues, presentation halls and luxury apartments. The latter account for at least half of the upper floors. The complex was created by the Turkish company Ant Yapı Sanayi ve Ticaret Anonim Şirketi according to the design of NBBJ architects and was eventually completed in 2009.

  • height – 302 m (Moscow) and 257 m (St. Petersburg);

  • floors – 76 (Moscow), 65 (St. Petersburg), 17 (dome building);

  • area of the facility – 288,680 sq. m;

  • developer – Capital Group;

  • cost - 450 million dollars.

"Northern Tower"

This is a business center that has received a BREEAM certificate for greening. There are offices, a cafe, a concert hall, a fitness center, a medical facility, and a parking lot. The Northern Tower was completed in 2008.

  • height – 108 m;

  • floors – 27;

  • area of the facility – 135,000 sq. m;

  • developer – “Northern Tower”;

  • architect – “Project Institute No. 2”;

  • Developer – Strabag.

"IQ-quarter"

This is the main transport hub of Moscow-City, as it is designed to connect it with Sheremetyevo and Vnukovo airports by rail. The complex was commissioned in 2016. It combines a hotel, a parking lot, an office building, residential and retail space.

  • height – 172.8 m;

  • floors – 22 (hotel), 34 and 43;

  • area of the facility – 228,000 sq. m;

  • developer – GALS-Development;

  • Architect – NBBJ;

  • developer – Ant Yapı Sanayi ve Ticaret Anonim Şirketi.

"Empire"

The complex is called a vertical city because it conveniently combines commercial, office and residential spaces. It was completed in 2011.

  • height – 238.6 m;

  • floors – 60;

  • area of the facility – 203,191 sq. m;

  • developer – Solvers;

  • Architect – NBBJ;

  • Developer – Enka.

"Evolution"

The most fascinating twisted tower "Evolution" was completed in 2015. It houses offices, retail space, and restaurants.

  • height – 255 m;

  • floors – 54;

  • area of the facility – 169,000 sq. m;

  • developer – "Snegiri";

  • Architect – Tony Kettle;

  • Developer: City Palace LLC.

Unfinished objects

There are still 5 objects under construction. First of all, these are 2 towers "Neva Towers", the height of which will be 337 m (residential building, 79 floors) and 290 m (office building, 65 floors).

Also this:

  • MFC on site No. 15, including office space and apartments;

  • MFC on site No. 4, designed for 71 floors of apartments and offices;

  • MFC on site No. 20, designed for 54 floors, which will house office space, apartments and infrastructure facilities;

  • 10-storey business center City Point;

  • One Tower.

Transport accessibility

The Moscow-City International Business Center was conceived to relieve the historical center of the capital. Therefore, it has a good transport interchange. The following are located in the immediate vicinity:

  • third transport ring;

  • Zvenigorodskoe highway;

  • Kutuzovsky Prospect;

  • Krasnogvardeisky passage;

  • Presnenskaya embankment.

All roads in the Moscow-City area have been reconstructed. But the problem of traffic jams in the morning hours is still relevant and requires finding new solutions. Therefore, in the near future, it is planned to build new roads and multi-lane expressways that will connect Moscow-City with the main transport arteries of the city. For parking personal vehicles, there are underground and above-ground parking lots on the territory of the complex.

You can also get to Moscow City by metro. The following stations are located 300–500 m from different skyscrapers:

  • Exhibition;

  • Business center;

  • International.

The IQ quarter has a transport hub that helps you quickly get to the Big City from Sheremetyevo and Domodedovo airports by modern high-speed train.



Show more Hide

History of Moscow-City

1991. Beginning of the Moscow City project
1991. Beginning of the Moscow City project

The construction of the century began in the mid-90s on the site of a former quarry and quarries in the area of Presnenskaya Embankment. It became the initial stage of the implementation of the large-scale program "Big City" . The initiator of the idea was the architect Boris Ivanovich Thor.

1991
1992. Continuation of design
1992. Continuation of design

Continuation of the design of the Moscow International Business Center "Moscow-City". The management company OAO "City" (today PAO "City") was organized. It is still engaged in the management and development of the MIBC, and is also the lessee of the land under the complex. Its owner is the "Solvers" group.



1992
1993. Preparatory work and site clearance
1993. Preparatory work and site clearance

Preparatory work is underway and issues are being resolved regarding the clearing of the territory from existing buildings for the construction of the future City. A documentary base is being developed regulating the planned development of Moscow-City.



1993
1996. Beginning of construction of the Bagration Bridge and Tower 2000
1996. Beginning of construction of the Bagration Bridge and Tower 2000

The beginning of construction of the pedestrian bridge Bagration” across the Moscow River and the first tower of the City – “Tower 2000” . Investments amounted to approximately 100 million US dollars. The objects were built according to the initial project of Boris Thor (the initial development plan was not taken into account further)

1996
1997. The Bagration Bridge was built
1997. The Bagration Bridge was built

The Bagration pedestrian bridge (named after the commander-in-chief of the 2nd Western Army at the beginning of the war of 1812, Pyotr Bagration) was opened. Its length is 214 m, width 16 m, and height 14 m. The total area of the bridge is 13,655 sq. m. The bridge has 2 levels connected by numerous stairs and escalators.

1997
2001. The “Tower 2000” was built
2001. The “Tower 2000” was built

“Tower 2000” (the building of the “Reforma” foundation - the original name) was completed in 2001. Its height is 130 m. “Tower 2000” has 34 floors, all of which are reserved for offices.

2001
2002. Launch of the Eurasia Tower project
2002. Launch of the Eurasia Tower project

The Eurasia project was launched. It involved the construction of a 71-story office and hotel complex with a total area of 208.3 thousand square meters in Moscow City.


2002
2003. Launch of the “Towers on the Embankment” project
2003. Launch of the “Towers on the Embankment” project

The project "Towers on the Embankment" developed by architects Inan Vehbi and Osturk Olcay was started by the Turkish company Enka. It was completed in 2003 and Enka immediately began construction of the first object. This was made possible by the fact that the project was divided into 3 parts.

2003
2004. Start of the project “City of Capitals”
2004. Start of the project “City of Capitals”

The Capital City project began construction in 2003, but was soon frozen after changes were made to the complex's design. Construction resumed in 2005.

2004
2004. Launch of construction of the multifunctional complex “Federation”
2004. Launch of construction of the multifunctional complex “Federation”

Construction of the Federation complex begins on the 3rd section of the Moscow International Business Center. The foundation is based on a massive concrete slab made of 14 thousand cubic meters of concrete (recorded in the Guinness Book of Records)

2004
2004. Block A “Tower on the Embankment” was commissioned
2004. Block A “Tower on the Embankment” was commissioned

Delivery and commissioning of the 17-storey building of the complex "Tower on the Embankment" block "A"

2004
2004. Construction of the Northern Tower complex was launched
2004. Construction of the Northern Tower complex was launched

Start of construction of the Northern Tower complex   - one of the lowest buildings in Moscow City.

2004
2004. Start of work on the central core of Moscow-City
2004. Start of work on the central core of Moscow-City

Laying the foundation stone for the Central Core building (TRC "Afimall", "Novotel") one of the most complex in terms of design buildings of the Moscow-City International Business Center, located on plots 6, 7 and 8.

2004
2005. Start of designing the Evolution Tower
2005. Start of designing the Evolution Tower

The Scottish bureau RMJM begins designing the "City Palace Tower" (later the "Evolution" tower) in the form of a spiral as a projection of the "yin-yang" symbol, symbolizing a dancing couple - the bride and groom. A wedding palace was planned at the foot, but this idea was later abandoned.

2005
2005. Block B “Tower on the Embankment” was commissioned
2005. Block B “Tower on the Embankment” was commissioned

The construction company ENKA has commissioned a 27-storey building of the complex "Tower on the Embankment" block "B" (block B)

2005
2005. Design of the Mercury Tower
2005. Design of the Mercury Tower

Design of Mercury City Tower (Mercury Tower, Golden Tower) on Lot 14 begins

2005
2006. Construction of the business complex “Empire” began
2006. Construction of the business complex “Empire” began

Start of construction of the building of the business complex "Empire" (first stage). Initially, on the 4th plot, a multifunctional leisure complex "Aquapark" with a hotel with a total area of 61,322 m² was to be built.

2006
2007. The last block of the “Tower on the Embankment” complex was completed
2007. The last block of the “Tower on the Embankment” complex was completed

The construction of the final building "Tower on the Embankment" (block C) is completed. The 60-story tower is 4 meters higher than the Moscow Triumph Palace and in 2007 became the tallest building in Russia and Europe.

2007
2007. Work on the project of the tower "Russia"
2007. Work on the project of the tower "Russia"

The beginning of construction work on the Rossiya Tower on site 17-18 of the Moscow-City International Business Center.

2007
2007. The Northern Tower complex was completed
2007. The Northern Tower complex was completed

The construction of the Northern Tower has been completed. The building was the third to be commissioned in the City area after Tower 2000 and the Embankment Tower.

2007
2008. Construction of the Evolution Tower began
2008. Construction of the Evolution Tower began

Construction of the Evolution skyscraper begins. In August 2011, Gazprombank opened a 7-year credit line of $345 million for the developer of the Evolution Tower to complete construction.

2008
2008. Launch of construction of the Eurasia Tower
2008. Launch of construction of the Eurasia Tower

Construction has begun on the Eurasia Tower, the only steel tower in Moscow City; all the others are made of concrete.

2008
2009. The multifunctional complex “City of Capitals” was built
2009. The multifunctional complex “City of Capitals” was built

On plot 9, the construction of the multifunctional complex "City of Capitals" has been completed - a complex of two high-rise towers: "Moscow" (73 floors) and "Saint Petersburg" (65 floors) with an 18-story connecting part on plot 9 of the Moscow-City district

2009
2009. Zero cycle of the MFC "Mercury" and slowdown of works
2009. Zero cycle of the MFC "Mercury" and slowdown of works

The zero cycle of works has been completed - the "wall in the ground" and underground floors of the multifunctional complex "Mercury Tower" , although the project was initially planned to be completed in 2009, but the developer "Mercury Development" preferred to slow down the work so as not to bring the facility to the market during the crisis.

2009
2010. Start of construction of the “IQ-quarter”
2010. Start of construction of the “IQ-quarter”

Construction of the IQ-quarter tower has begun, consisting of 3 buildings with a total area of 425,800 m2.

2010
2010. The City of Capitals in the TOP-10 Skyscrapers of the World
2010. The City of Capitals in the TOP-10 Skyscrapers of the World

The Moscow Tower in the Capital City multifunctional complex was included in the TOP-10 best skyscrapers in the world as part of the Emporis Skyscraper Award (Emporis Standards), awarded for its aesthetic appearance and compatibility with the urban environment.

2010
2011. Opening of the AfiMall City complex
2011. Opening of the AfiMall City complex

On May 22, 2011, the grand opening of the shopping and entertainment complex "AfiMall City" (Central Core) took place.

2011
2011. The business center “Empire” was put into operation
2011. The business center “Empire” was put into operation

Commissioning of a 60-storey skyscraper building - the Empire Business Center .

2011
2012. “City of Capitals” took 1st place among skyscrapers in Europe
2012. “City of Capitals” took 1st place among skyscrapers in Europe

The Capital City multifunctional complex took first place among European skyscrapers in the tournament of the most popular buildings at the SkyscraperCity forum, but failed to reach the finals in the world tournament, losing by only 8% to the famous New York skyscraper Empire State Building.

2012
2012. Launch of construction of the OKO multifunctional complex
2012. Launch of construction of the OKO multifunctional complex

Construction of the OKO multifunctional complex , a skyscraper complex located on site 16 Moscow-City, has begun. The name OKO is an abbreviation for "unified crystal bases"

2012
2013. The Mercury Tower was completed
2013. The Mercury Tower was completed

The construction of the 75-storey skyscraper with an orange façade , Mercury City Tower , has been completed. Even before the work is completed (the upper mark of the structure is 340.1 meters), it has become the tallest building in Europe, overtaking London's The Shard skyscraper.

2013
2013. Launch of the “Grand Tower” project
2013. Launch of the “Grand Tower” project

On site 15, construction of the 62-storey building "Grand Tower" (Grand Tower Moscow City) has begun (the project was frozen for a long time, but work resumed in 2019).

2013
2013. Construction of the Neva Towers complex began
2013. Construction of the Neva Towers complex began

Construction has begun on the high-rise complex "Neva Towers" , occupying plots 17 and 18. Earlier, it was planned to build the "Russia" tower with a record height of 612 meters on this site.

2013
2013. Launch of the second stage of the tower “Empire II”
2013. Launch of the second stage of the tower “Empire II”

It became known about the construction of the second stage of the tower "Imperia Tower Imperia" . The project consisted of 2 separate buildings with an area of 115,800 m², on a common stylobate with underground parking and a park, which is located on an overpass and connects the complex with the embankment of the Moscow River.

2013
2014. The Evolution Tower multifunctional complex was completed
2014. The Evolution Tower multifunctional complex was completed

The construction of the multifunctional complex "Evolution Tower" has been completed. Each floor (there are 51 of them) is turned relative to the previous one by 3 degrees, thus the building is "twisted" by 156 degrees.

2014
2014. Construction of the Eurasia Tower is completed
2014. Construction of the Eurasia Tower is completed

Construction of the business center has been completed "Eurasia" is a 309 m high skyscraper located on the 12th section of the City.

2014
2014. “Federation Tower” is the tallest building in Russia and Europe
2014. “Federation Tower” is the tallest building in Russia and Europe

On November 25, 2014, when the top mark of the Vostok Tower of the Federation Complex under construction reached 343 meters, the Federation Tower became the tallest building in Russia and Europe.

2014
2015. Evolution Tower - finalist of “CTBUH Awards 2015”
2015. Evolution Tower - finalist of “CTBUH Awards 2015”

The Evolution Tower became the best glass and translucent structure project at the IV Russian architectural competition “Glass in Architecture”, a finalist of the Best Skyscrapers of the World competition “CTBUH Awards 2015” in the nomination “Best High-Rise Building in Europe” and the winner of the NOPRIZ competition as “Best MFC Project”

2015
2016. The project of the Vostok Tower of the Federation Tower multifunctional complex was completed
2016. The project of the Vostok Tower of the Federation Tower multifunctional complex was completed

The construction of the Vostok skyscraper (previously known as Tower A), a complex of high-rise buildings called the Federation Tower, has been completed. The Vostok Tower has 102 floors (including 95 above-ground and 7 underground), and 18 high-speed elevators are installed in it.

2016
2016. The skyscrapers of the multifunctional complex “OKO” were built
2016. The skyscrapers of the multifunctional complex “OKO” were built

On plot 16, two skyscrapers of the OKO multifunctional complex were built, one of which has 49 floors and is 245 meters high (North Tower), and the other has 85 floors and is 354 meters high (South Tower).

2016
2016. The IQ-quarter project was completed
2016. The IQ-quarter project was completed

On site 11, work has been completed on the IQ-quarter multifunctional complex (IQ Quarter) , consisting of three towers, including offices, apartments, a café, a hotel, parking, and a skating rink.

2016
2017. The Federation Tower project is fully completed
2017. The Federation Tower project is fully completed

On November 15, 2017, the construction of the 374-meter-high Federation Tower complex was fully completed. The International Council on Tall Buildings and Urban Habitat (CTBUH) recognized it as the tallest skyscraper in Europe for 2017. The skyscrapers stand on a slab of 14 cubic meters of concrete, a fact that is included in the Guinness Book of Records.

2017
2018. Start of construction of the Capital Towers complex
2018. Start of construction of the Capital Towers complex

Start of construction of a complex of 3 towers of the Capital Towers complex (two 212 meters high and the dominant 270 meters high) with apartments, not apartments in the City (City Tower, River Tower and Park Tower)

2018
2019. Commissioning of the first stage of Neva Towers
2019. Commissioning of the first stage of Neva Towers

The first stage of Neva Towers has been put into operation, including a 79-story tower with 848 apartments.

2019
2019. “Federation Tower” - “The best real estate in the world” – Grand Prix of the International Property Awards
2019. “Federation Tower” - “The best real estate in the world” – Grand Prix of the International Property Awards

Federation Tower has won the world-famous and honorable quality mark in the field of real estate – the Grand Prix of the International Property Awards 2019-2020 - “The best real estate in the world”

2019
2019. Start of construction of the Headliner residential complex
2019. Start of construction of the Headliner residential complex

In 2019, construction of a new residential complex Headliner, consisting of 10 buildings, began near Moscow-City.

2019
2019. Start of construction of the supertall skyscraper ONE TOWER
2019. Start of construction of the supertall skyscraper ONE TOWER

In 2019, construction began on the multifunctional 109-storey residential complex One Tower (1 Tower) with a height of 442.8 m.

2019
2020. Start of construction of the iCity office skyscraper
2020. Start of construction of the iCity office skyscraper

Construction has begun on the iCity office skyscraper, consisting of two towers, Time Tower (141.2 meters) and Space Tower (256.7 meters)

2020
2020. The Neva Towers business complex is completed
2020. The Neva Towers business complex is completed

Commissioning of the 2nd 68-storey tower of the Neva Tower s complex and completion of the entire complex.

2020
2022. A new 400-meter Palitra tower is planned
2022. A new 400-meter Palitra tower is planned

A new project of a 400-meter tower with the working title Palitra in Moscow-City in the style of K. Malevich from Gals Development has been announced

2022
2022. The Grand Tower skyscraper under construction is renamed Moscow Towers
2022. The Grand Tower skyscraper under construction is renamed Moscow Towers

New skyscraper Grand Tower Moscow City has received the official name Moscow Towers

2022
2023. Construction of the multifunctional complex Dom Dau has been approved
2023. Construction of the multifunctional complex Dom Dau has been approved

Start of construction of the 85-storey residential complex "Dom Dau" near Moscow-City

2023
2024. Construction of Moscow Towers completed
2024. Construction of Moscow Towers completed

NF Group has completed construction of the multifunctional complex Moscow Towers .

2024
2024. The first cube of concrete was poured into the foundation of the Dau House
2024. The first cube of concrete was poured into the foundation of the Dau House

July 30, 2024 at the construction site "Dau House" Pouring of the foundation slab has begun in Moscow City.

2024
2025. Wildberries&Russ headquarters project and Bagration Bridge reconstruction approved
2025. Wildberries&Russ headquarters project and Bagration Bridge reconstruction approved

The Moscow Committee for Architecture has approved the project for the Wildberries&Russ business center, which will appear on Krasnopresnenskaya Embankment next to the Bagration Bridge in Moscow-City.

2025
2025. The One Tower residential complex project has been approved
2025. The One Tower residential complex project has been approved

MR Group announced an updated concept for the One Tower residential complex on the first site of Moscow City. Two towers up to 91 storeys high will be connected by a glass bridge. The project was developed by Sergey Kuznetsov and the GENPRO bureau.

2025
2025. The Big City project is only 80% complete
2025. The Big City project is only 80% complete

The Big City project is 80% complete, which means there are many new and exciting projects and solutions ahead. Follow the news with us.

2025

Development plans for Moscow City

With the completion of the construction of the Moscow-City International Business Center, the grandiose project of the Big City is just beginning to be implemented. In the near future, it is planned to cover another 100 hectares of land adjacent to the Presnenskaya Embankment up to Khoroshevskoye Highway.

After the reorganization of the future development zone and the elimination of industrial enterprises in the surrounding areas, it is planned to build administrative-business and trade-recreational complexes, as well as housing. It is planned to build about 21 million square meters of real estate, which will require more than 100 billion dollars in investment.

The project has already built the International Trade Center. The project to build the Mirax Plaza hotel and business complex has recently begun, and the Paradise Life project has received government approval.

With the implementation of all plans, "Big City" will become a new and very prestigious area of the capital.

Any questions about the City?

Ask us. We know everything about Moscow-City.

By sending a message you agree to the privacy policy
personal data processing
and user agreement
Buy a ticket to the observation deck